The electrical layout is decided in a few hurried minutes on site, usually with the wiring contractor pointing at walls, and then lived with for twenty years. That is why so many Indian homes have the same complaints: not enough sockets, so extension boards snake across the floor; a switchboard behind the opened door, or on the wrong side of the bed; no point where the water purifier, the microwave or the washing machine eventually goes; and a distribution board where one tripped MCB kills half the house. None of these are faults in the wiring; they are faults in the planning. The wire itself rarely fails. What fails is the decision about how many points to provide, where to put them, and how to divide them across circuits.
Point planning is the craft of making those decisions on paper, room by room, before the walls are chased. It has two halves. The first is the point count and position: how many light points, fan points, switch locations and socket outlets each room needs, and at what height, worked out from how the room will actually be used rather than from a standard template. The second is the circuit and load design: grouping those points into lighting and power circuits, giving each its own protective device, sizing the main and the sub-circuits, and estimating the total load so the sanctioned supply and the distribution board are adequate. The first half is where a homeowner can contribute most; the second half is a licensed electrician's responsibility, following the wiring code.
This article sets out electrical load and point planning for a 3 BHK home in practical terms: how to count and place points room by room, how to split the home into lighting, power and dedicated circuits, how MCBs, RCCBs and the distribution board are organised, how to estimate the load and sanctioned supply, and at what heights switches and sockets belong. It also gives indicative October 2026 costs and a checklist. The circuit and protective-device practice follows IS 732 and the National Building Code of India 2016, Part 8; the exact design is a licensed electrician's job, and the aim here is to let an owner plan well and ask the right questions.
Counting the points room by room
Point planning starts with a walk through each room, imagining a day in it, and listing every place that will ever need a switch or a socket. A bedroom needs a ceiling light and fan, a two-way switch at the door and the bed, bedside sockets on both sides for lamps and phone chargers, a socket for a television or an air conditioner, and a point for a future study table. A living room needs the lighting circuits already discussed, television and media sockets, a few general sockets along the walls, and a point for an air conditioner. A kitchen is the socket-hungriest room of all, needing dedicated outlets for the refrigerator, microwave, mixer, water purifier, chimney, induction and any built-in oven, each at worktop or appliance height. Counting generously at this stage costs a few hundred rupees per extra point; adding one after the walls are closed costs far more and leaves a scar. The rule is to plan for the appliances a household will own in ten years, not only the ones it owns today.
| Room | Light / fan | Sockets (general) | Dedicated points |
|---|---|---|---|
| Living / dining | Layered + fan | 8–10 (5A and 16A) | AC, television, router |
| Master bedroom | Light + fan, 2-way | 4–6 (bedside both sides) | AC, television |
| Bedroom 2 / 3 | Light + fan, 2-way | 3–4 each | AC each |
| Kitchen | Ambient + task | 8–12 at worktop height | Fridge, hob, chimney, purifier, microwave |
| Bathrooms | Light + exhaust | 1–2 (shaver / shelf) | Geyser, exhaust fan |
| Utility / balcony | Light | 2–3 (weatherproof) | Washing machine, pump |
Heights for switches and sockets
Where a point sits matters as much as whether it exists. The old habit of putting the main switchboard at around 1200 to 1300 millimetres has given way to a lower, more comfortable switch height of about 1050 to 1200 millimetres, within easy reach and clear of most furniture, while general convenience sockets sit low at about 300 to 450 millimetres so cords do not trail up the wall. Kitchen sockets go above the worktop, roughly 1050 to 1150 millimetres, so appliances plug in without cords crossing the counter. Bedside sockets belong at about 600 to 750 millimetres, at the height of a nightstand. A television point sits behind the screen, and an air conditioner point high near the ceiling at about 2100 to 2200 millimetres. Getting these heights right is what separates a home that feels effortless from one where every appliance fights the furniture — and, crucially, a switchboard must never end up hidden behind an opened door, the single most common and most avoidable placement mistake.
Splitting the home into circuits
A home is not wired as one big loop; it is divided into circuits, each a separate run of cable from the distribution board protected by its own device, so that a fault or an overload on one trips only that circuit and leaves the rest of the house working. The wiring code, IS 732, limits a lighting final sub-circuit to a modest load and a sensible number of points — commonly taken as not more than about ten points or around 800 watts on one lighting circuit — so a 3 BHK needs several lighting circuits rather than one. Power sockets are grouped onto 16 ampere circuits, again a few rooms' worth per circuit, not the whole house. And the heavy appliances — each air conditioner, the geyser, a kitchen hob or oven, a washing machine, a water pump — are given their own dedicated circuits, because a single such load can approach or exceed the capacity of a shared circuit on its own. Splitting the home this way is what makes it safe and convenient; lumping too much onto one circuit is what causes nuisance tripping and overheated wiring.
| Circuit | Typical MCB | Wire size | Serves |
|---|---|---|---|
| Lighting | 6 A | 1.0–1.5 sq mm | ≤ ~10 points / ~800 W per circuit |
| General power | 16 A | 2.5 sq mm | 16 A socket outlets, a few rooms |
| Air conditioner | 20–32 A | 4 sq mm | One AC per circuit |
| Geyser | 16–20 A | 2.5–4 sq mm | One geyser per circuit |
| Kitchen appliances | 16–20 A | 2.5–4 sq mm | Hob / oven / heavy appliance |
| Water pump | 16–20 A | 2.5–4 sq mm | Pump on its own circuit |
MCBs, the RCCB and the distribution board
The distribution board, or DB, is the home's electrical hub, and how it is organised decides how safe and how convenient the installation is. Each circuit leaving the board has its own miniature circuit breaker, or MCB, rated to the circuit — typically 6 amperes for lighting, 16 amperes for power sockets, and 20 to 32 amperes for heavy dedicated loads — which trips on an overload or a short circuit and protects that circuit's cable. Protecting people rather than cables is the job of the residual current device: an RCCB, usually rated at 30 milliamperes for a home, which trips the instant it detects current leaking to earth through a person or a fault, and is the single most important life-safety device in the house. Good practice gives wet areas and socket circuits RCCB protection, provides proper double earthing, and labels every MCB clearly so that the right one can be found in a hurry. A DB where nothing is labelled and one tripped MCB kills half the house is a planning failure, not a wiring one.
Sizing the board and the incoming supply follows from the load. The main switch and the service cable must carry the whole home's demand, and the DB must have enough ways not just for today's circuits but for a few spare ways for future additions — an extra air conditioner, an inverter, a car charger. Leaving two or three spare ways in the board at the outset costs almost nothing and saves replacing the whole board later. The earthing, the main switch rating and the RCCB selection are all parts of a design that a licensed electrician must sign off; the owner's contribution is to insist on proper circuit splitting, RCCB protection, clear labelling and spare capacity, and to resist the contractor's temptation to save a few hundred rupees by crowding everything onto fewer circuits.
Estimating the load and the supply
The connected load is the sum of everything that could draw power, and the sanctioned supply is what the utility agrees to provide; the two are related but not equal, because not everything runs at once. A rough load estimate adds up the lights and fans, the sockets with a realistic allowance, and each heavy appliance at its rated power — air conditioners at around 1.2 to 1.8 kilowatts each, a geyser at 2 to 3 kilowatts, a microwave at around 1.2 kilowatts, an induction hob at around 2 kilowatts — then applies a diversity factor, because a household never runs every one of these simultaneously. For a typical 3 BHK the connected load commonly comes to the order of eight to twelve kilowatts, while the sanctioned demand applied for is usually lower, often in the region of five to seven kilowatts, reflecting that diversity. The exact sanctioned load is worked out with the electrician and applied for from the utility; over-sanctioning wastes fixed charges, while under-sanctioning trips the main when the family switches on two air conditioners and the geyser together.
| Load group | Indicative rating | Note |
|---|---|---|
| Lights and fans (whole home) | 0.5–1.0 kW | Low with LED lighting |
| General sockets (with diversity) | 1.5–3 kW | Not all in use at once |
| Air conditioner (each) | 1.2–1.8 kW | One dedicated circuit each |
| Geyser | 2–3 kW | Dedicated circuit |
| Kitchen (microwave, induction, etc.) | 2–4 kW | Dedicated circuits |
| Typical 3 BHK sanctioned demand | 5–7 kW | After diversity; confirm with utility |
The figure below shows how the estimate is built: the small, steady loads of lights and fans at the base, a realistic allowance for general sockets above them, and then the heavy appliances — the air conditioners, geyser and kitchen loads — stacked on top, which dominate the total. The diversity factor is what separates the connected load, the full stack, from the sanctioned demand applied for, because no household runs every air conditioner, the geyser and the full kitchen at the same instant. Getting this stack right matters in two directions: a sanctioned load set too low trips the main supply on a summer evening when several heavy loads coincide, while one set too high means paying the utility's fixed charges every month for capacity that is never used. The electrician works the real numbers from the actual appliance list; the stack here is only to show where the kilowatts come from.
- Count points room by room from how the home will be used in ten years, not only today.
- Fix switch and socket heights deliberately — switchboard 1050–1200 mm, general socket 300–450 mm, kitchen socket above the worktop.
- Never place a switchboard behind an opened door or on the wrong side of a bed.
- Split the home into several lighting circuits (≤ ~10 points each) and separate power circuits — not one big loop.
- Give every heavy load — each AC, geyser, pump and kitchen appliance — its own dedicated circuit and correctly sized MCB.
- Protect socket and wet-area circuits with a 30 mA RCCB, and provide proper double earthing.
- Label every MCB in the distribution board so the right one can be found in seconds.
- Leave two or three spare ways in the DB for future additions — an inverter, an extra AC, a car charger.
- Match wire size to the circuit — roughly 1.0–1.5 sq mm lighting, 2.5 sq mm power, 4 sq mm heavy loads.
- Have a licensed electrician size the main, the MCBs and the sanctioned load, and sign off the installation.
What it costs, and where home wiring is heading
Electrical work is a small fraction of a home's finishing cost, and under-spending on it is the falsest of economies, because the whole installation is buried behind plaster and tile. A standard wiring point — the concealed conduit, the fire-retardant cable, a modular switch or socket and the labour, excluding the light fitting or appliance — commonly runs in the region of ₹350 to ₹900 per point indicatively, with data and heavy appliance points higher. The distribution board, MCBs and RCCB are a modest assembly against the safety they provide. Against all of this, the cost of chasing a wall open after the home is finished, to add the socket that was not planned, is many times the cost of having provided it at the outset. The direction of travel is towards more points, more circuits and more protection — homes now plan for air conditioners in every room, electric vehicle charging, inverters and solar, and smart switching — all of which make generous point planning and spare DB capacity more valuable, not less. The indicative October 2026 figures here are for budgeting only and must be confirmed locally.
| Item | Unit | Indicative Oct 2026 cost |
|---|---|---|
| Standard wiring point | Per point | ₹350–900 |
| Data / network point | Per point | ₹800–2,000 |
| Dedicated heavy-appliance point | Per point | ₹900–2,500 |
| Distribution board with MCBs + RCCB | Per board | ₹6,000–20,000 |
| Extra circuit after walls close | Per circuit | ₹3,000–8,000+ |
Frequently asked questions
How many points does a 3 BHK need?
There is no single number, because it depends on how the home will be used, which is exactly why a point-by-point count beats a template. As a guide, a 3 BHK commonly ends up with well over a hundred points once lights, fans, switches, general sockets and dedicated appliance points are all counted — the kitchen and living room alone account for a large share. The right approach is to walk each room, imagine the appliances and furniture of ten years hence, and list every switch and socket needed, counting generously because an extra point now costs a few hundred rupees while one added after the walls close costs far more.
What size MCB goes on which circuit?
Typically a 6 ampere MCB protects a lighting circuit, a 16 ampere MCB a general power circuit of 16 ampere sockets, and a 20 to 32 ampere MCB a heavy dedicated load such as an air conditioner, with the exact rating matched to the appliance and the cable by the electrician. The MCB protects the cable, so its rating must suit the wire size — roughly 1.0 to 1.5 square millimetre for lighting, 2.5 square millimetre for power, and 4 square millimetre for heavy loads. These are indicative values following IS 732; the licensed electrician sizes each device for the actual load and cable.
What is the difference between an MCB and an RCCB?
An MCB, a miniature circuit breaker, protects the cable: it trips on an overload or a short circuit to stop the wire overheating. An RCCB, a residual current circuit breaker, protects people: it trips the instant it detects current leaking to earth — for example through someone who has touched a live part — usually at 30 milliamperes for a home. They do different jobs and a safe installation needs both: MCBs on each circuit against overload and short circuit, and an RCCB covering socket and wet-area circuits against electric shock. The RCCB is the single most important life-safety device in the home.
What load should I sanction for a 3 BHK?
The connected load of a typical 3 BHK — everything added up — commonly comes to around eight to twelve kilowatts, but the sanctioned demand applied for from the utility is usually lower, often about five to seven kilowatts, because a household never runs every appliance at once and a diversity factor is applied. The right figure depends on how many air conditioners, geysers and heavy appliances the home has and will add. Work it out with the electrician: over-sanctioning wastes monthly fixed charges, while under-sanctioning trips the main supply when several heavy loads run together.
Sources & standards
- Bureau of Indian Standards, IS 732 — Code of Practice for Electrical Wiring Installations
- National Building Code of India 2016, Part 8 — Building Services (electrical installations)
- Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations — earthing and protection
- Bureau of Indian Standards, IS 8061 / IS 3043 — guidance on electrical installation planning and earthing
- Neufert, Architects' Data — electrical points, switch and socket heights
- Price ranges: indicative October 2026 estimates — confirm locally before budgeting