GST 2.0 on Building Materials: What It Changed for Homes

GST 2.0 on Building Materials: What It Changed for Homes — cover

Ten percentage points. That is how much the GST on a bag of cement fell on 22 September 2025, when the rate rationalisation that the government and the trade began calling "GST 2.0" came into force. For eight years cement had sat in the top 28 per cent slab alongside luxury goods, and every house, compound wall and RCC slab in the country carried that tax. Overnight it dropped to 18 per cent. Stone blocks, sand-lime bricks and bamboo flooring fell to 5 per cent, and air-conditioners joined cement in moving from 28 to 18.

Homeowners then heard two opposite stories. One said that building had become dramatically cheaper; the other said that nothing had changed because interior quotes looked the same as before. Both are half right. The reform cut tax sharply on a few heavy structural materials, but most of the finishing materials that make up an interior quote — paint, tiles, plywood, sanitaryware, glass, wires, switches, lamps, furniture — had already been brought down to 18 per cent in 2017 and 2018, and they stayed there. This guide separates the two, using only the rates published by the GST Council and the Press Information Bureau, and shows what the change is actually worth on a house, a flat purchase and an interior project. It is general information for budgeting, not tax advice; a chartered accountant should confirm the rate on any specific invoice.

What changed on 22 September 2025

The GST Council approved the changes at its 56th meeting on 3 September 2025, and the new rates applied from 22 September 2025. The headline was structural: the old four-slab system of 5, 12, 18 and 28 per cent was collapsed into two main rates — a merit rate of 5 per cent and a standard rate of 18 per cent — with a special 40 per cent rate kept for a short list of demerit goods such as tobacco products, aerated drinks and larger cars and motorcycles. No building material was placed in the 40 per cent list. In practice that meant anything used in construction that had been at 28 per cent came down to 18, and several items that had been at 12 per cent went down to 5.

To see why cement was the big story, it helps to look back. When GST began on 1 July 2017, many building and interior goods sat at 28 per cent: cement, ceramic tiles, sanitaryware, plywood and particle board, glass, wires and switches, paint, furniture and mattresses among them. In November 2017 the Council moved a long list of these — tiles, sanitaryware, plywood, boards, glass, wires, switches, lamps, wallpaper, marble and granite slabs, furniture and mattresses — down to 18 per cent. In July 2018 paints and varnishes followed. Cement was the notable holdout, and it stayed at 28 per cent until GST 2.0. Separately, from 1 April 2019 the tax on new residential flats was restructured to 1 per cent for affordable housing and 5 per cent for other homes, without input tax credit. Fig. 1 puts these steps on one line.

Fig. 1 — GST on building materials, 2017–2025 1 Jul 2017GST beginscement, tiles, ply,paint at 28 % 15 Nov 2017tiles, sanitaryware,ply, glass, wires,furniture 28 → 18 % Jul 2018paints andvarnishes28 → 18 % 1 Apr 2019new flats: 1 %affordable, 5 %others, no ITC 22 Sep 2025GST 2.0: cement28 → 18 %, stoneblocks 12 → 5 % Most finishing materials reached 18 % in 2017–18. GST 2.0 mainly moved the last heavy item, cement, and a few stone and bamboo products. Dates are the effective or announced dates of each change. Source: GST Council and PIB press releases (23rd, 28th, 33rd–34th and 56th meetings).
Fig. 1 — GST on building materials, 2017 to 2025: the five steps that matter

Before and after: rates on building materials

The table below lists only the construction-related changes that appear in the official GST Council and PIB material for the September 2025 reform. It is deliberately short. Many websites published longer lists within days of the announcement, and several of them showed items such as tiles or plywood "falling from 28 to 18 per cent" in 2025 — but those items had already been at 18 per cent since November 2017. Where a material is not in this table, the safest assumption is that its rate did not change in 2025, and the invoice HSN code should be checked.

ItemRate before 22 Sep 2025Rate from 22 Sep 2025Who feels it
Cement (Portland and other hydraulic cements)28 %18 %Anyone building or doing civil work: slabs, columns, plaster, masonry, compound walls
Marble and travertine blocks12 %5 %Mainly stone processors; finished slabs are a separate entry
Granite blocks12 %5 %Mainly processors; small knock-on effect on slab prices
Sand-lime bricks12 %5 %Projects using this specific brick type
Bamboo flooring and bamboo joinery12 %5 %Homes choosing bamboo floors or bamboo doors and frames
Stone inlay and stone art ware (handicraft entries)12 %5 %Inlay panels, stone artefacts, some pooja-room work
Air-conditioners28 %18 %Every home or office buying split or ducted AC units
Dishwashers; LCD/LED televisions above 32 inches28 %18 %Kitchen and living-room appliance budgets
Fig. 2 — GST paid on ₹100 of material (pre-tax), before and after Cement Marble / graniteblocks Sand-lime bricks Tiles, plywood,sanitaryware Paint, wires,switches, glass ₹28 before₹18 after ₹12 before₹5 after ₹12 before₹5 after ₹18 before₹18 after — no change ₹18 before₹18 after — no change before 22 Sep 2025 from 22 Sep 2025 The two bottom groups are most of an interior quote. They were cut to 18 % in 2017–18, not in 2025. Rates as published by the GST Council and PIB; always confirm the HSN-wise rate printed on the invoice.
Fig. 2 — Tax paid on ₹100 of material before and after GST 2.0

Materials that stayed at 18 per cent

Most of what a homeowner sees and touches after the structure is finished was untouched by GST 2.0, because it had already been brought down years earlier. The November 2017 changes moved ceramic tiles of all kinds, sanitaryware, plywood and particle and fibre boards, wooden articles and frames, glass and mirrors, wires, cables, switches and sockets, lamps and light fittings, wallpaper, marble and granite slabs and tiles, and furniture, mattresses and bedding from 28 to 18 per cent. Paints, varnishes, enamels and putty-type products, together with storage and immersion water heaters, followed in July 2018. With the 28 per cent slab now gone for everything except the 40 per cent demerit list, these items simply remain in the 18 per cent standard rate.

Material groupRate todayAt 18 % sinceNote for budgeting
Ceramic and vitrified tiles18 %November 2017No 2025 change; tile price moves come from brand and freight, not tax
Sanitaryware (WCs, basins and parts)18 %November 2017Faucets and fittings are separate entries; check the invoice
Plywood, particle board, fibre boards18 %November 2017The core of every wardrobe and kitchen; no 2025 change
Glass and mirrors18 %November 2017Shower partitions, mirrors, glass shutters
Wires, cables, switches, sockets, lamps18 %November 2017Electrical rewiring and lighting budgets unchanged by GST 2.0
Marble and granite slabs and tiles (finished)18 %November 2017Only the raw blocks moved to 5 % in 2025
Furniture, mattresses, bedding18 %November 2017Some bamboo and cane items have their own entries; check the HSN
Paints, varnishes, enamels, putty-type products18 %July 2018Painting quotes did not change because of GST 2.0

Steel is the other large structural input, and it was already in the 18 per cent slab before September 2025; it was not part of the 2025 changes. That matters for anyone estimating a house, because steel and cement together make up a large share of the structural material bill. Only one of the two became cheaper in tax terms.

What the cement cut is worth on a house

Cement does not appear as a separate line in most homeowners' minds, but it runs through every stage of a building: footings, columns, beams and slabs, block or brick masonry, internal and external plaster, flooring beds, and compound walls. The useful question is not "how much cheaper is cement?" but "how much of my project is cement, and how much tax did that portion carry?" The worked example below uses round figures as an illustration. The cement value should be taken from the contractor's bill of quantities or the actual purchase bills for each project, because it varies with structure, number of floors and design.

Line (illustrative house, about 2,000 sq ft built-up)Before 22 Sep 2025From 22 Sep 2025Difference
Cement purchased, value before tax (assumed for the example)₹3,00,000₹3,00,000—
GST on cement₹84,000 (28 %)₹54,000 (18 %)₹30,000 less
Cement bill including GST₹3,84,000₹3,54,000₹30,000 less (≈ 7.8 %)
Construction cost at ₹2,200–2,800 per sq ft (standard band on this site)₹44–56 lakh₹44–56 lakh less the savingSaving ≈ 0.5–0.7 % of the total

On these assumptions the cement cut is worth about ₹30,000 on a ₹44–56 lakh house — real money, but well under one per cent of the total. A bigger or heavier building, a basement, a raft foundation or a long compound wall will push the cement share up and the saving with it; a modest single-storey home will see less. The point of the exercise is to stop two mistakes: assuming the reform has made construction dramatically cheaper, and assuming it has done nothing at all.

Fig. 3 — Cement runs through the whole structure RCC slabs and beams RCC columns masonry mortar and plaster footings, plinth, floor beds Illustrative numbers cement value: ₹3.0 lakh tax at 28 %: ₹84,000 tax at 18 %: ₹54,000 saving: ₹30,000 house: ₹44–56 lakh ≈ 0.5–0.7 % of total Replace ₹3.0 lakh with the cement value in your own bill of quantities. Steel, also a big structural input, was already at 18 % and did not change. Interiors (wood, paint, tiles) carry no cement saving at all.
Fig. 3 — Where the cement saving lands in a house budget (illustrative)

Who actually pockets the saving

For a family building its own house, the saving reaches them only if the contractor or dealer reduces the tax-inclusive price. A homeowner cannot claim input tax credit on materials or works contracts used to construct their own house — the CGST Act blocks credit for construction of immovable property on one's own account — so whatever GST is charged is a final cost. That makes it worth checking the cement line of every bill raised after 22 September 2025. Where a contractor quoted a lump-sum rate per sq ft before the change and is building after it, the contract terms decide who benefits; a clause that says rates are "inclusive of taxes as applicable" is worth discussing openly rather than assuming.

Interior projects: why quotes barely move

An interior quote is built almost entirely from items that were already at 18 per cent: plywood and boards, laminates and veneers, hardware, glass, tiles, paint, wires, switches, lamps and furniture. A fit-out by an interior firm is normally billed either as a works contract for the whole job or as separate supplies and services, and in both cases the usual GST on the invoice for a home interior is 18 per cent. Design fees are a service and also carry 18 per cent. None of that moved in September 2025. The table shows how GST sits on top of the Surat 2BHK bands used across this site, which are quoted before GST.

Surat 2BHK, 1000 sq ft (bands used on this site)Interior cost before GSTGST at 18 %Total with GST
Budget₹8–11 lakh₹1.44–1.98 lakh₹9.44–12.98 lakh
Mid-range₹13–18 lakh₹2.34–3.24 lakh₹15.34–21.24 lakh
Luxury (from)₹23 lakh₹4.14 lakh₹27.14 lakh upwards
Design fee example₹2,50,000₹45,000₹2,95,000
What GST 2.0 changed hereNothing on boards, paint, tiles, hardwareRate still 18 %Only a new AC or TV bought within the job is cheaper

There are three places where an interior budget does feel GST 2.0. First, air-conditioners: split units moved from 28 to 18 per cent, so a household buying three or four units at the same time as its interiors sees a real saving on that line. Second, a large television above 32 inches and a dishwasher, both of which also moved from 28 to 18. Third, any civil work inside the interior job — a new partition in blocks, re-plastering, a raised floor bed or a kitchen platform base — uses cement, and that portion of the material bill now carries less tax. Bamboo flooring and bamboo joinery and stone inlay work are niche, but where they are chosen they now attract 5 per cent.

Buying a flat: where GST sits in the price

For flat buyers the reform changed less than the headlines suggested, because the GST on a new home is not charged on materials at all. Since 1 April 2019, the construction of residential apartments in a project has been taxed at 1 per cent for affordable housing and 5 per cent for other housing, without input tax credit for the builder. Affordable housing in this scheme means a carpet area of up to 60 sq m in metropolitan cities or 90 sq m elsewhere, with a value of up to ₹45 lakh. Because the builder cannot take credit for the GST paid on cement and other inputs, those taxes are part of the builder's cost. A lower rate on cement therefore reduces the builder's cost; whether it reduces the flat's price depends on the builder and the market, not on any automatic rule.

What is being boughtGST on the price (general position)Effect of GST 2.0What to check
Under-construction flat, affordable category1 %, without input tax creditRate unchanged; builder's cement cost lowerWhether the price per sq ft was revised for new bookings
Under-construction flat, other residential5 %, without input tax creditRate unchanged; builder's cement cost lowerThat GST is shown separately from the base price
Completed flat sold after the completion or occupancy certificateNo GST on the saleNone on the priceDate of the certificate versus date of payments
Resale flat from an individual ownerNo GST on the saleNoneStamp duty and registration are separate state levies
Interior work on any flatUsually 18 % on the interior invoiceNone, except ACs and cement-based civil workWhether the quote is before or after GST

Two practical points follow. A buyer comparing an under-construction flat with a completed one should compare like with like: the GST on the under-construction home is a real additional cost, while the completed home carries no GST but may carry a higher base price. And neither choice affects the 18 per cent that will later be paid on the interiors. The comparison of timing and interior cost between the two kinds of flat is covered in detail in this site's guide to ready-to-move and under-construction homes.

Reading invoices and passing on the cut

The lower rate helps only if it appears on the bill. A GST invoice from a registered dealer or contractor should show the supplier's GSTIN, the HSN or service accounting code, the taxable value, and the tax split into CGST and SGST for a sale within Gujarat, or IGST for an inter-state sale. For cement after 22 September 2025, the combined rate should read 18 per cent — 9 per cent CGST plus 9 per cent SGST within the state. Any invoice still showing 28 per cent on cement after that date deserves a question.

Fig. 4 — What to look for on the bill TAX INVOICESupplier GSTIN: 24XXXXXXXXXXXXX Place of supply: GujaratDate: after 22 Sep 2025 ItemHSNTaxable ₹CGSTSGSTTotal ₹ Cement, 50 kg bags252310,0009 % 9009 % 90011,800 Before the change the same line read 14 % + 14 % = 28 % and a total of ₹12,800. Inter-state purchase: one IGST line at 18 % instead of CGST + SGST. Example figures only — the taxable value is whatever the dealer charges. ↑ HSN column: tells you which rate applies ↑ CGST + SGST: 9 % + 9 % = 18 % for cement now Keep invoices for every major purchase: they prove what tax was paid, help with warranty claims, and let a chartered accountant check the rate if a dispute or a business-use question arises later.
Fig. 4 — Anatomy of a GST invoice line for cement (within one state)

For contractors and interior firms, the question is usually not the rate on their own invoice — which stays at 18 per cent for most interior work — but whether their purchase cost for cement-based work fell and whether that was reflected in their rate. On a pure interior job the answer is "very little", and a homeowner should not expect a lower per-sq-ft rate for wardrobes or kitchens because of GST 2.0. On a civil or turnkey job with significant masonry, plaster or RCC, it is reasonable to ask how the cement saving has been treated for work done after 22 September 2025.

For businesses fitting out offices and shops

A registered business doing a fit-out is in a different position from a homeowner, because it may be able to claim input tax credit on some purchases. Credit is generally blocked for works contracts and goods used to construct immovable property on the business's own account, which usually covers built-in work that is capitalised as part of the building, while movable furniture and equipment such as loose desks, chairs and air-conditioners are treated differently. The boundary depends on facts and accounting treatment, so the line between "built-in" and "movable" should be agreed with the business's chartered accountant before the quote is split into items.

Where GST on construction is heading

The direction of travel since 2017 has been consistent: fewer slabs, and building materials pulled out of the luxury bracket. With cement at 18 per cent, almost every mainstream construction and interior material now sits at either 5 or 18 per cent, which makes estimating simpler and reduces the number of disputes about classification. Several questions remain open and are worth watching rather than predicting. The real-estate rates of 1 and 5 per cent without input tax credit leave builders unable to recover the GST they pay on inputs, which is why a rate cut on cement does not automatically change flat prices. Electricity, petrol and diesel — which affect transport and site costs — remain outside GST. And the Council continues to review the rate structure, so any budget prepared today should list GST separately, so that it can be updated if a rate changes before the work is billed.

PeriodStructureWhat it meant for building budgets
July 2017Four main slabs: 5, 12, 18, 28 %Cement, tiles, sanitaryware, plywood, paint and furniture all at 28 %
November 2017 – July 2018Large cuts from 28 to 18 %Most finishing materials and paint reach 18 %; cement stays at 28 %
April 2019Residential projects at 1 % or 5 % without ITCFlat buyers pay GST on the price, not on materials
September 2025Two main slabs, 5 and 18 %, plus 40 % demeritCement to 18 %; stone blocks, sand-lime bricks, bamboo flooring to 5 %
From herePeriodic review by the GST CouncilQuote GST as a separate line so budgets can be updated

Ten rules for budgeting with GST 2.0

  • Treat GST 2.0 as a cement and appliance story; do not expect lower rates on tiles, plywood, paint, sanitaryware or wiring, which were already at 18 per cent.
  • Ask every dealer and contractor whether quoted rates include GST, and write the answer into the quote.
  • For a house, pull the cement value out of the bill of quantities and calculate the saving yourself: tax at 18 per cent instead of 28 per cent on that value.
  • Check cement invoices dated on or after 22 September 2025 for 9 + 9 per cent (or 18 per cent IGST), not 14 + 14 per cent.
  • For contracts signed before the change but billed after it, read the tax clause and agree in writing how the cement saving is treated.
  • Budget 18 per cent on top of interior quotes and design fees that are stated before GST.
  • Buy air-conditioners, large televisions and dishwashers with the interior budget in mind; these moved from 28 to 18 per cent.
  • When comparing an under-construction flat with a completed one, include the 1 or 5 per cent GST on the under-construction price.
  • Keep every GST invoice; they matter for warranties, disputes and, for businesses, for any credit that may be available.
  • Ask a chartered accountant before relying on a rate for a business fit-out or an unusual material; this guide is general information, not tax advice.

Frequently asked questions

What is the GST on cement now?

18 per cent, from 22 September 2025. It was 28 per cent from the start of GST in July 2017 until then. Within a state the invoice shows 9 per cent CGST and 9 per cent SGST; an inter-state purchase shows 18 per cent IGST.

Did GST on tiles and plywood come down in 2025?

No. Ceramic tiles, plywood, particle and fibre boards, sanitaryware, glass, wires, switches and furniture were moved from 28 to 18 per cent in November 2017, and they remain at 18 per cent. Lists that show these items falling in 2025 are comparing with the original 2017 rate.

Is GST on paint 18 or 28 per cent?

18 per cent. Paints, varnishes and enamels were cut from 28 to 18 per cent by the GST Council in July 2018 and were not changed by GST 2.0, which is why painting quotes did not move in September 2025.

Does GST 2.0 make an under-construction flat cheaper?

Not automatically. The GST on the flat is still 1 per cent for affordable housing and 5 per cent for other homes, without input tax credit. The cement cut lowers the builder's cost, but whether that is passed on in the price per sq ft is a commercial decision. A completed flat sold after the completion or occupancy certificate carries no GST on the sale.

How much GST is charged on interior design work?

For a home interior, a registered firm usually charges 18 per cent on the works contract or on the separate supplies and services, and 18 per cent on design fees. GST 2.0 did not change these rates. A small unregistered contractor will not charge GST, but their price already includes the tax they paid on materials.

Sources & standards

  1. GST Council, 56th meeting (3 September 2025) — press release on GST rate rationalisation and the PIB explainer on the Next-Gen GST reforms, effective 22 September 2025: cement 28 → 18 %; marble/travertine and granite blocks, sand-lime bricks, bamboo flooring and joinery 12 → 5 %; ACs, dishwashers and TVs above 32 inches 28 → 18 %
  2. GST Council, 23rd meeting (10 November 2017) — press release: ceramic tiles, sanitaryware, plywood and boards, glass, wires and switches, lamps, wallpaper, marble and granite slabs, furniture and mattresses 28 → 18 %
  3. GST Council, 28th meeting (21 July 2018) — press release: paints and varnishes, putty-type products, storage water heaters 28 → 18 %
  4. GST Council, 33rd meeting (24 February 2019) and 34th meeting (19 March 2019) — press releases on residential real estate: 1 % affordable and 5 % other housing without input tax credit, from 1 April 2019
  5. Central Goods and Services Tax Act, 2017 — Section 17(5) (blocked credits for construction of immovable property) and Schedule III (sale of a building after completion certificate)
  6. Central Board of Indirect Taxes and Customs (CBIC) — GST rate notifications and HSN-wise rate schedules for goods and services
  7. Price ranges: indicative October 2026 estimates — confirm locally before budgeting. GST information is general, not tax advice; confirm rates for a specific invoice with a chartered accountant