Every interior project in India reaches the same moment: the drawings are ready, the 3D views look right, and a PDF arrives with a total at the bottom that is several lakh rupees larger than the family expected. Most people read that number first, then scroll up looking for something to cut, and finally compare it with another firm's total that is "two lakh cheaper". Very few read the quotation the way a contractor or quantity surveyor does — line by line, unit by unit, specification by specification — and that is exactly where the money is decided.
A quotation is not a price list. It is the written promise of what will be built, in what material, to what size, with which hardware, at what rate, under which conditions. A cheaper quote is often a smaller scope, a thinner board, a cheaper hinge, an unmeasured loft, a ceiling quoted per sq ft of plain gypsum when the drawing shows coves, or a long list of exclusions on the last page. Families who sign on the total discover these differences during execution, as "extras". Families who read the quotation properly discover them before signing, when they cost nothing to fix.
This guide walks through an interior quotation the way Aaditya Interior's team reviews one before it goes to a client: the parts of the document, the units of measurement and what each actually measures, the specification lines that drive price, a worked example for a mid-range 3BHK, taxes and exclusions, payment terms, how to compare three quotes fairly, and the red flags that predict disputes. Prices are indicative October 2026 figures consistent with the cost guides elsewhere on this blog.
Why interior quotations look the way they do
The modern interior quotation grew out of two older traditions. The first is the carpenter's estimate. For decades, most Indian homes were furnished by a mistri working on site: the family or the designer bought the plywood, laminate and hardware, and the carpenter quoted labour — sometimes per day, more often per square foot of finished furniture. Because material and labour were bought separately, the client saw exactly what went in, but nobody owned the whole result, and the cost was known only at the end.
The second tradition is the civil contractor's bill of quantities, or BOQ — a schedule listing every item of work with its description, unit, quantity and rate, prepared from drawings and measured according to agreed rules. Indian civil practice measures work according to the IS 1200 series of standards, which set out how each trade is measured, and public works departments publish schedules of rates in the same format. When design-and-build interior firms and modular factories became common from the 2000s and 2010s, they borrowed the BOQ format and the per-square-foot rate from these two traditions: furniture priced per sq ft of front elevation, ceilings per sq ft of area, painting per sq ft of paintable surface, electrical work per point.
Today a quotation may come from an independent designer with a separate contractor, from a design-and-build studio, from a modular-kitchen brand, or from an online package company quoting per BHK. The format differs, but a fair quotation of any type answers the same seven questions: what, how big, how many, in what material, with what hardware and finish, at what rate, and on what terms. Anything a quotation does not state in writing should be assumed to be the cheapest option or not included at all.
Anatomy of a quotation: the parts and the columns
A complete interior quotation has a cover section, a bill of quantities divided by trade or by room, a summary, and terms. The cover section identifies the firm with its registered address and GSTIN, the client, the site address, the date, a quotation number, a validity period, and — most importantly — the drawing set and revision it is based on. A quotation that does not reference drawings has nothing to be checked against. The BOQ is the heart of the document. Each row is one item, and each item needs its own description, size, unit, quantity, rate and amount.
| Column or section | What it must contain | What to check |
|---|---|---|
| Item number and location | Room and item, e.g. "3.1 Master bedroom wardrobe" | Every item on the drawings has a row; nothing is merged into "misc." |
| Description and specification | Board, thickness, grade, finish, edge band, hardware brand and type | Vague words such as "premium" or "branded" without a name or grade |
| Size | Width × height (× depth) in mm or ft | Matches the drawing; lofts and returns listed separately |
| Unit | sq ft, running ft, nos, point, lump sum | Unit suits the item; no lump sums for measurable work |
| Quantity | Calculated from the size | Recalculate a few rows yourself |
| Rate | Price per unit | Compare with market bands; note if GST is inside or outside |
| Amount | Quantity × rate | Arithmetic is right; totals add up |
| Terms and exclusions | Validity, payment, timeline, warranty, variations, exclusions | Long exclusion lists hidden on the last page |
Units of measurement: what you are actually paying for
The single most misunderstood part of an interior quotation is the unit. A rate of ₹1,600 means nothing until it is clear whether it is per square foot of front elevation, per square foot of floor area, per running foot, or per piece. Different firms use different units for the same item, and the same unit can be measured in different ways. The table summarises the units in common Indian use and how each is usually measured.
| Unit | Used for | How it is measured | Common trap |
|---|---|---|---|
| Sq ft of elevation (front area) | Wardrobes, lofts, TV units, crockery units, vanities | Overall width × overall height of the front face | Loft or filler counted at full rate; height measured to slab instead of to unit top |
| Running foot (rft) | Modular kitchens, cove lighting, skirting, profiles | Length along the wall or counter | Unclear whether wall units are included in the kitchen rft |
| Sq ft of area | False ceilings, flooring, wall panelling | Plan area or wall area as installed | Coves and drops measured as flat area; wastage not stated |
| Sq ft of paintable area | Painting, texture, wallpaper | Wall and ceiling surfaces, openings deducted per agreed rule | Openings not deducted; ceiling counted twice |
| Per point | Electrical and plumbing work | Each switch, socket, light or water outlet | "Point" definition differs — wire length and switch type unstated |
| Numbers (nos) | Hardware, lights, appliances, accessories | Count of pieces | Brand and model not named |
| Lump sum (LS) | Demolition, debris removal, cleaning, small civil items | Fixed price for a defined task | Large items in lump sum cannot be checked or varied fairly |
| Per sq ft of carpet area | Package quotes for a whole home | Carpet area of the flat | Scope inside the package unclear; extras outside it |
Sq ft of elevation is the unit that causes most confusion. It measures the front face of a unit, not the material used. A wardrobe 2100 mm wide and 2100 mm high has 4.41 m², or about 47.5 sq ft, of elevation, whether it is 450 mm or 600 mm deep and whether it has four shelves or ten. That is why the rate per sq ft must be read together with depth, internal configuration and accessories: a firm quoting ₹1,400 for a 450 mm deep wardrobe with plain shelves may be dearer than one quoting ₹1,700 for a 600 mm deep wardrobe with drawers and a trouser rack included.
The same discipline applies to every unit. A modular kitchen quoted per running foot should state whether that foot includes base units only, base and wall units, or base, wall and tall units, and whether the countertop, sink, hob cut-out and accessories sit inside or outside the rate. A false ceiling quoted at ₹70 per sq ft is a plain gypsum ceiling; a ceiling with coves, drops and profile slots belongs in the ₹80–180 band, and the cove itself may be measured separately in running feet. An electrical "point" should define the wire size and length allowance, conduit type, switch and socket range — a point of 6 m of wire in an existing conduit is a very different job from a new point chased into a wall.
Specifications: the lines that decide the price
Two quotations for the same wardrobe can differ by forty per cent and both be fair, because they describe different wardrobes. The specification line is where that difference lives. For built-in furniture, the minimum a specification should state is the carcass board and its grade (for example BWR or BWP plywood conforming to IS 303 or IS 710, or HDHMR), its thickness (18 mm for carcasses is standard, with 6–9 mm or 12 mm backs), the shutter board and finish (laminate thickness, acrylic, PU paint or veneer with polish), the edge banding (thickness and material), the inner surface finish, the hinges and drawer channels by type and brand, and the handles.
| Vague line (avoid) | Proper specification (ask for) | Why it matters |
|---|---|---|
| Wardrobe in premium ply | 18 mm BWR plywood carcass (IS 303), 9 mm back, 0.8 mm inner laminate | "Premium" can mean any grade or thickness |
| Laminate finish shutters | 1 mm decorative laminate, named range and shade code, 2 mm PVC/ABS edge band | Thinner laminates and paper edge tape chip and peel |
| Branded hardware | Soft-close concealed hinges and full-extension soft-close channels, brand and series named | Hardware fails first; unbranded parts cost a fraction |
| Kitchen with all accessories | List: cutlery tray, plate rack, bottle pull-out, corner unit — each with size and brand | "All" becomes whatever was cheapest |
| Gypsum ceiling with cove | 12.5 mm gypsum board on GI frame, cove profile per drawing, cove measured in rft | Framing and cove detail drive the rate |
| Premium paint | Named emulsion range, putty + primer + 2 coats, surfaces listed | Coats and preparation are where corners are cut |
| Lighting as per design | Each fitting type, wattage, colour temperature, CRI and quantity | Allows like-for-like comparison and checking on site |
Material grade claims should be checkable. Plywood carries an IS mark and a licence number on genuine branded sheets; laminate packs carry a shade code and thickness; hardware arrives in the brand's packaging. A good contract states that the client or designer may inspect material on delivery and reject anything that does not match the specification. This single clause does more to keep a quotation honest than any amount of bargaining over the rate.
A worked example: mid-range 3BHK quotation
The table below shows a mid-range quotation for a 3BHK of about 1,250 sq ft carpet area, using midpoints of the bands from this blog's 3BHK cost guide. It is illustrative, not a price for any particular project, but it shows how the sections of a real quotation add up and where the money goes. Note that the site work and contingency line is real money: minor civil changes, plumbing tweaks, debris removal, protection and a buffer for what is found when walls are opened.
| Section | Typical contents | Illustrative amount (₹ lakh) | Share |
|---|---|---|---|
| Kitchen and countertop | L-shape modular kitchen, quartz counter ≈ 45 sq ft | 2.85 | 15 % |
| Wardrobes | Three rooms, ≈ 160 sq ft elevation incl. lofts | 2.80 | 15 % |
| Beds and side tables | Three beds with storage | 2.20 | 12 % |
| Living, foyer, pooja, utility, study | TV and crockery units, shoe unit, mandir, utility, desk | 2.65 | 14 % |
| False ceiling and painting | ≈ 800 sq ft gypsum with coves; premium emulsion | 1.95 | 10 % |
| Electrical and lighting | Point changes, cove LED, panels, pendants | 1.25 | 7 % |
| Bathroom fittings | Three baths, mid-range sets with labour | 1.35 | 7 % |
| Curtains and soft furnishings | Fabric, tracks, blinds | 1.45 | 8 % |
| Site work, civil changes and contingency | Minor civil, plumbing, debris, protection, buffer | 2.50 | 13 % |
| Total before GST and design fee | ≈ ₹1,520 per sq ft of carpet | 19.00 | 100 % |
Read in this way, the quotation tells a story. If the furniture share is much lower than about half, check whether beds, the study or the crockery unit have been left out. If the site work line is missing entirely, expect it to return as extras. If the electrical line is very small, the lighting design may not have been priced at all. And if GST is not mentioned, ask whether every rate includes it or excludes it — on a ₹19 lakh project the difference is over three lakh rupees.
Exclusions, provisional sums, contingency and GST
The gap between the quoted total and the final bill almost always comes from four places. The first is exclusions: items that are not part of the quotation at all. Loose furniture, appliances, ACs, curtains, decor, light fixtures chosen later, society deposits and debris charges are commonly excluded, and that is fine as long as they are listed and the family budgets for them. The second is provisional sums — allowances for work that cannot be measured until site conditions are known, such as civil repairs behind old tiles or electrical upgrades after a load check. A provisional sum should state what it covers and the rates at which the actual work will be billed.
The third is contingency. Elsewhere on this blog, a contingency of about five to eight per cent agreed in advance is recommended for larger homes, and the 3BHK cost guide builds a 10–15 per cent buffer into its site-work line for renovation work. A quotation without any contingency is not cheaper; it simply moves the uncertainty to the client. The fourth is GST. Interior contracts and most materials commonly attract GST at 18 per cent; the quotation should show it as a separate line with the firm's GSTIN, and the tax invoice should match it. Rates should be marked clearly as inclusive or exclusive of GST.
| Item | How it should appear | Typical allowance (indicative Oct 2026) | Question to ask |
|---|---|---|---|
| Loose furniture | Listed as excluded or quoted separately | ₹1.5–5 lakh+ for a 3BHK by level | Which pieces are in, which are out? |
| Appliances | Excluded; sizes fixed in drawings | Retail prices | Are cut-outs sized for the chosen models? |
| Electrical upgrades | Provisional sum with per-point rates | ₹30,000–70,000 | Has a load calculation been done? |
| Civil repairs after opening | Provisional sum with item rates | ₹20,000–45,000 per room opened | At what rates will extra work be billed? |
| Contingency | Stated percentage or amount | 5–8 % new; 10–15 % renovation | Who approves spending it? |
| GST | Separate line with GSTIN | Commonly 18 % on interior contracts | Are rates inclusive or exclusive? |
| Design and supervision fee | Separate unless design-and-build | Per sq ft, lump sum or about 8–12 % of project cost | How many site visits and revisions are included? |
Payment terms, timeline, variations and warranty
The terms page decides how the relationship works when something goes wrong, so it deserves as much attention as the prices. A balanced execution payment schedule starts with a booking advance of about 10–20 per cent, ties later payments to visible progress — material delivered, carcasses installed, shutters and finishes complete — and keeps a retention of about 5–10 per cent until the snag list is closed. The design fee, where it is separate, is usually paid in stages tied to concept, detailed drawings and supervision. A schedule that asks for most of the money before work is visible on site shifts all of the risk to the client.
The production payment in the schedule above is the one point where money runs ahead of visible work: factory-made furniture needs material bought and cut before anything reaches site. That is normal and fair, provided the client can see the material order or visit the factory, and provided the schedule pulls back into balance at installation. Variations — any change after signing — should be priced in writing before they are carried out, using the quotation's own rates where possible. The quotation should also state the timeline with its dependencies (the client's approval of finishes, the society's work hours, appliance delivery), and the warranty: what is covered, for how long, and what voids it. Hardware warranties are given by brands; workmanship warranty is given by the firm, and the two should be listed separately.
Comparing three quotations fairly
Comparing quotations is a normalising exercise. Before anyone looks at totals, the three documents must be brought to the same scope and the same specification. Make a single sheet with one row per item from the drawings and one column per firm. Fill in each firm's size, unit, specification and amount. Wherever one firm has left something out, add a realistic figure for it; wherever one has quoted a lower grade, note the difference. Only then compare totals. The example below shows how a quote that looks cheapest becomes the most expensive once it is normalised.
| Line | Firm A | Firm B | Firm C |
|---|---|---|---|
| Quoted total (before GST) | ₹19.0 lakh | ₹16.8 lakh | ₹17.9 lakh |
| Carcass board | 18 mm BWR plywood | 18 mm MR plywood | 18 mm BWR plywood |
| Hardware | Soft-close, brand named | "Branded", unnamed | Soft-close, brand named |
| Lofts | Included | Excluded | Included |
| Beds | Three, with storage | Two only | Three, with storage |
| Site work and contingency | Included | "At actuals" | Included, provisional |
| Normalising additions | — | + lofts, third bed, site work, board upgrade ≈ ₹3.4 lakh | + cove lighting missing ≈ ₹0.4 lakh |
| Comparable total | ₹19.0 lakh | ≈ ₹20.2 lakh | ≈ ₹18.3 lakh |
After normalising, Firm C is the lowest and Firm B — the cheapest on paper — is the highest, because its quotation left out items the family will still need and specified a board grade that the others did not. This is the most common pattern in interior pricing. It does not mean the cheapest quotation is dishonest; it means the cheapest quotation is often a different product. The normalised sheet also makes negotiation fair: the family can ask Firm A why its wardrobe rate is higher than Firm C's for the same specification, instead of asking everyone for "best price".
Red flags that predict extras and disputes
| Red flag | What it usually hides | What to ask for |
|---|---|---|
| Single per-sq-ft rate for the whole home | Undefined scope; items outside the package billed as extras | An itemised BOQ against the drawings |
| No drawing reference or revision | Nothing to check sizes against | Drawing list and revision on the cover page |
| "Premium", "branded", "best quality" without names | The cheapest option that fits the word | Brand, series, grade and thickness on every line |
| Large lump sums for measurable work | Padding, or no way to vary fairly | Unit, quantity and rate |
| "At actuals" without rates | Open-ended billing | Rates for likely extras written in advance |
| Most of the payment before site work | Client financing the project; weak leverage | Milestones tied to visible progress and a retention |
| No GST line or GSTIN | Tax added later, or an unregistered vendor | GST shown separately; GSTIN on the quotation |
| No validity date | Prices revised after signing | Validity period and price-escalation clause |
Where interior quotations are going
Quotations are slowly becoming data rather than documents. Design software can now produce a bill of quantities directly from the 3D model, so that moving a wall or changing a shutter finish updates the quantities and the price together. Factories that cut panels on CNC machines can quote from their own cutting lists, which makes board consumption measurable rather than estimated. Project-tracking apps let clients see each line's status — ordered, delivered, installed — and tie payments to those milestones. And GST e-invoicing for larger businesses has made tax invoices more structured and easier to check. None of this replaces careful reading. A model-generated BOQ is only as good as the specification behind it, and a client still needs to know what a sq ft of elevation measures.
Rules for reading any interior quotation
- Check the drawing reference first — the quotation must name the drawing set and revision it prices.
- Read the unit before the rate: sq ft of elevation, running foot, sq ft of area, per point, nos or lump sum.
- Recalculate three or four rows yourself — size to quantity, quantity × rate to amount.
- Insist on board, thickness, finish, edge band and hardware brand on every furniture line.
- List the exclusions on one page and budget for them separately.
- Make sure provisional sums state what they cover and the rates for actual work.
- Confirm whether rates include GST, and that the GSTIN is on the quotation.
- Tie payments to visible progress, keep a 5–10 per cent retention, and price every variation in writing before it is done.
- Normalise competing quotes to the same scope and specification before comparing totals.
Frequently asked questions
What is a BOQ in interior design?
A BOQ, or bill of quantities, is the itemised schedule at the heart of a quotation. It lists every item of work with its description, specification, size, unit of measurement, quantity, rate and amount. It lets the client check what is included, compare quotations line by line, and price any changes fairly.
What does per sq ft mean in an interior quotation?
For furniture it usually means square feet of front elevation — width × height of the unit's face — not floor area and not material used. For ceilings and flooring it means area, and for painting it means paintable surface. Always check which one the quotation uses and what depth, internal fittings and finish the rate covers.
Is GST charged on interior design work?
Yes. Interior contracts and design services commonly attract GST, typically at 18 per cent. The quotation should show GST as a separate line with the firm's GSTIN, and rates should be clearly marked as inclusive or exclusive of tax. Confirm the current rate and the firm's registration before signing.
How much advance should I pay an interior designer?
For execution, a booking advance of about 10–20 per cent is common and balanced, followed by payments linked to material delivery, installation and finishing, with 5–10 per cent held until snags are closed. Design fees, where separate, are usually paid in stages. Be cautious of schedules that ask for most of the money before work is visible on site.
Why is one interior quotation so much cheaper than another?
Usually because it describes less work or lower specifications: a lower board grade, unnamed hardware, missing lofts or beds, or site work left "at actuals". Normalise the quotations to the same scope and specification before comparing totals; the cheapest on paper is often not the cheapest in the end.
Sources & standards
- Bureau of Indian Standards — IS 1200 series: Method of measurement of building and civil engineering works
- Bureau of Indian Standards — IS 303 (plywood for general purposes) and IS 710 (marine plywood)
- Central Board of Indirect Taxes and Customs — GST on works contracts and services; checking GSTIN and tax invoices
- Indian Contract Act, 1872 — offer, acceptance and the terms of a written contract
- Consumer Protection Act, 2019 — rights of consumers buying services
- National Building Code of India 2016, Part 8 (Building Services) — electrical installations referenced in electrical scope
- Council of Architecture — guidance on conditions of engagement and professional fees
- Price ranges: indicative October 2026 estimates — confirm locally before budgeting